About the Client
KIUMA is a large, rural Christian ministry complex in Southern Tanzania, housing approximately 1,000 people. It serves the surrounding community through a 160-bed hospital, schools, a vocational training centre, and other outreach programmes.
Project Challenge
The existing electrical system was unsafe, inefficient, and inadequate for the campus’s current and future needs. The project required a complete, turnkey replacement of the entire electrical infrastructure to create a reliable and sustainable power solution for the ministry.
MMM South Africa’s Involvement
MMM South Africa conducted the initial on-site assessment that identified the critical need for a system overhaul. During the project’s execution, MMM South Africa served as the donor’s representative on-site, providing essential oversight and coordination for the duration of the project.
Technical disciplines involved
This was a comprehensive Engineering, Procurement, and Construction (EPC) project led by CONCO, who provided the detailed design and project management.
- EMI participated in a consulting role during the design phase to ensure the client’s engineering standards were met.
- The project spanned multiple disciplines including Electrical Engineering (hybrid power systems), Civil & Structural Engineering, and overall Project Management.
Key result, learning or implementation outcome
The project successfully delivered a modern and robust hybrid power plant through a collaborative effort. CONCO executed the detailed design and construction, EMI provided crucial engineering standards and consulting, and MMM South Africa ensured project integrity as the on-site donor representative. The new system provides KIUMA with a safe, reliable, and sustainable energy future, integrating diesel, solar, and battery storage with a connection to the national grid.
Project Location
KIUMA Complex, Tunduru, Tanzania